Computing People Intentions


The Intentware Project Plan

Galil Plan
  1. Automatic navigation User interface >>
  2. Declarative request User Interface
  3. Declarative report builder
  4. Declarative relational data or linked data definition

Gamla Plan

  1. Service modeling elements
  2. Intentional data store >>
  3. Generic actors links interface layer
  4. Intentional services engine

Goren Plan

  1. Services designer (services, data and actions dictionary)
  2. Workflow designer (objects and flows)
  3. Supervision designer (controls and alert events)
  4. Actors studio (build and test)
  5. Deployment studio (legacy software & people integration)
  6. Prototypes designer
  7. Project management studio
A. 120 days/3 devs
  1. 60 days, 2 devs
  2. 30 days, 2 devs
  3. 60 days, 2 devs
  4. 60 days, 3 devs

B. 170 days/3 devs

  1. 80 days, 3 devs
  2. 40 days, 2 devs
  3. 80 days, 3 devs
  4. 60 days, 2 devs

C. 225 days/3 devs

  1. 60 days, 3 devs
  2. 40 days, 2 devs
  3. 40 days, 2 devs
  4. 60 days, 2 devs
  5. 80 days, 3 devs
  6. 40 days, 2 devs
  7. 60 days, 3 devs

Project log is here.